Bentworth is set within a conservation area and offers a huge amount of architectural character and features all of which have been carried forward into the proposed design scheme. A full design management scheme has been carried out which include an initial cost plan, schedule of works, planning permission, building regulation approval, tender invitation process, nominating a principal contractor and project management.
ASP Murphy Builders have again been awarded the contract, we have worked together on numerous contracts and to date have seamlessly provided our clients with a quality end project that has been on budget and on time.
Existing
Existing
Existing
08/09/14 - Work Commencement
08/09/14 - Work Commencement
08/09/14 - Work Commencement
08/09/14 - Work Commencement
08/09/14 - Work Commencement
17/09/14 - Submerged oil tank construction
17/09/14 - Ready for concrete!
17/09/14 - Reinforced oversite for garage being carried out
17/09/14 - Extension foundations ready for concrete
25/09/14 - Open plan parking!
25/09/14 - The only way is up
30/09/14 - Nearly ready for roof
30/09/14 - Progress with super-structure
07/10/14 - Roof members
07/10/14 - Ready for roof tiles
07/10/14 - Saving date stone and re-locating to prime position
07/10/14 - In the dry!
14/10/14 - Sub-merged oil tank in place
14/10/14 - Natural slate roof covering
14/10/14 - In the dry!
14/10/14 - Structural supports in place
31/10/14 - Scafold down!
31/10/14 - Sliding Sash windows fitted in place
31/10/14 - Ready for the floor screed
07/11/14 - Internal opening to new dining area
07/11/14 - Working on the external drive
07/11/14 - Sneaky peak at the utility!
07/11/14 - Pointing of front elevation complete
07/11/14 - Starting on the patio area
07/11/14 - Hard at it, patio area being constructed
07/11/14 - External Oil fired combi boiler
17/11/14 - External works being carried out
17/11/14 - New shower with bi-folding doors
17/11/14 - Internals nearly complete
17/11/14 - Finishing touches to utility room
17/11/14 - Up and running!
10/12/14 - Electric entrance gates
10/12/14 - Oak framed garage construction
10/12/14 - Completed rear external
10/12/14 - Final part of project being constructed - Oak framed garage
06/02/15 - After waiting for the Oak Frame Joiner... Completion
06/02/15 - Joinery detail
06/02/15 - Electric gates in operation
06/02/15 - Safe walk area around submerged tank
06/02/15 - Garage completed
06/02/15